Thursday, October 24, 2019

Procedure of Contractual Claims in Construction

Procedure of Contractual Claims in Construction




In this article we will discuss about procedure of contractual claims in construction and notice of claims. So be sure to bookmark this article to check out future posts to learn valuable information on the other sources as well. Also you can share our valuable article with other professionals.

As a FIDIC 1999 Red Book,

"Within 42 days after the Contractor became aware (or should have become aware) of the event or circumstance giving rise to the claim, or within such other period as may be proposed by the Contractor and approved by the Engineer, the Contractor shall send to the Engineer a fully detailed claim which includes full supporting particulars of the basis of the claim and of the extension of time and/or additional payment claimed."

procedure of contractual claims in construction
procedure of contractual claims in construction

Notice of Claims

Notwithstanding any other provision of the Contract, if the Contractor intends to claim any additional payment pursuant to any Clause of these Conditions or otherwise, he shall give notice of his intention to the Engineer, with a copy to the Employer, within 28 days after the event giving rise to the claim has first arisen.



Contemporary Records of Claims

Upon the happening of the event referred to in notice of claims, the Contractor shall keep such contemporary records as may reasonably be necessary to support any claim he may subsequently wish to make. Without necessarily admitting the Employer's liability, the Engineer shall, on receipt of a notice under notice of claims, inspect such contemporary records and may instruct the Contractor to keep any further contemporary records as are reasonable and may be material to the claim of which notice has been given. The Contractor shall permit the Engineer to inspect all records kept pursuant to this Sub-Clause and shall supply him with copies thereof as and when the Engineer so instructs.

Substantiation of Claims

Within 28 days, or such other reasonable time as may be agreed by the Engineer, of giving notice under notice of claims, the Contractor shall send to the Engineer an account giving detailed particulars of the amount claimed and the grounds upon which the claim is based. Where the event giving rise to the claim has a continuing effect, such account shall be considered to be an interim account and the Contractor shall, at such intervals as the Engineer may reasonably require, send further interim accounts giving the accumulated amount of the claim and any further grounds upon which it is based. In cases where interim accounts are sent to the Engineer, the Contractor shall send a final account within 28 days of the end of the effects resulting from the event. The Contractor shall, if required by the Engineer so to do, copy to the Employer all accounts sent to the Engineer pursuant to this Sub-Clause.

Failure to Comply

If the Contractor fails to comply with any of the provisions of this Clause in respect of any claim which he seeks to make, his entitlement to payment in respect thereof shall not exceed such amount as the Engineer or any arbitrator or arbitrators appointed pursuant to Arbitration assessing the claim considers to be verified by contemporary records (whether or not such records were brought to the Engineer's notice as required under Contemporary Records and Substantiation of Claims).



Payment of Claims

The Contractor shall be entitled to have included in any interim payment certified by the Engineer pursuant to Clause 60 such amount in respect of any claim as the Engineer, after due consultation with the Employer and the Contractor, may consider due to the Contractor provided that the Contractor has supplied sufficient particulars to enable the Engineer to determine the amount due. If such particulars are insufficient to substantiate the whole of the claim, the Contractor shall be entitled to payment in respect of such part of the claim as such particulars may substantiate to the satisfaction of the Engineer. The Engineer shall notify the Contractor of any determination made under this.Sub-Clause, with a copy to the Employer.

Read more: How to Approach Delay Analysis in Construction Contract | EOT Claim

If u like this article then please comment us and share this article.


Read more article >>>



#contractual_claims
#notice of claims
#construction_claims
#claims
#contemporary records of claims
#substantiation of claims
#failure to comply
#payment of claims

No comments:

Post a Comment