Breaking

Sunday, December 29, 2019

What are kickers and Why?... we used kickers

What are kickers and Why?... we used kickers.




In this article, we will discuss concrete kicker, kicker construction, wall kicker, column kicker, etc.


wall kicker, kicker, concrete kicker

In the construction terminology that I Use, a kicker is a 50-150mm step that is provided at the Column/ Shear wall Base during the casting of the slab/ foundation. It is provided to ensure that the coordinates of the column/ wall are maintained uniformly between the slab and essentially throughout the structure.
kicker setting out for column-constructionway.blogspot.com
kicker setting out for column

somewhat like this...

Following the slab/ foundation casting, the shuttering for the column can be fixed directly on the kicker to ensure column location and base alignment is accurate.

Its purpose is to avoid uneven steel cover and Column/wall alignment issues which are almost impossible to rectify once the concrete is cast and can be easily identified/ rectified by providing a kicker.



The wrong practice associated with the provision of a kicker is that some contractors provide a kicker after casting the slab, which adds an additional unwanted construction joint in columns near the base where the shear is maximum and hence is unadvised. I would recommend that if you are providing a kicker it has to be provided during the slab itself as below.

The only disadvantage associated is that the initial preparation and casting time of the slab with the kicker is prolonged slightly, however, I believe the advantages of providing a kicker outweigh this problem.



What are kickers?:

A kicker is a small concrete plinth 50-150mm (2"-6") in height placed around a column base in order for you to quickly start your next stage column pour - it sets out the alignment pre-pour rather than post-pour (because if you need to move things, you can do it there and then). It is usually cast with the floor, pad, or raft foundation. Construction can be fiddly/slows concreting for the first stage foundation slightly, but lost time is usually made up in time at the column/wall erection stage (if you have crews that know what they are doing).
kicker formwork for column-constructionway.blogspot.com
the kicker in construction | 
kicker concreteing for column-constructionway.blogspot.com
kicker concreting for column
Having a kicker you can physically see what's not right both in terms of cover and by looking along the kicker bases give a quick visual indication of what needs to be moved. Obviously, your surveyor would set-up a local grid to set these things out. It is easier to look along a straight edge of columns than it is a long string line with wavy 32mm reinforcement starter bars (which are usually placed where they can due to base steel configuration).

The reason why we have column and wall kickers are as follows:



From Checking Engineers Perspective

Having a Kicker - Pros:

1. You can see any column or wall alignment issues immediately, fix any grid problems straight away (Once the concrete is cast and steel alignment problems exist, you don't have to cut the steel, just move it before you pour).

2. Makes the next stage construction (columns and walls) much faster as you only have to butt up against your formwork against the kicker (alignment is already done).

3. Gives additional level(concrete elevation) guides as well as screed rails, therefore, providing better elevation control.

4. Reduces the number of joints in the concrete. (you only have one joint where a second stage kicker would give you two. - NOT GOOD!)

Having a Kicker - Cons:

1. Slower (INITIAL) stage pouring, but less risky. Slightly more fiddly initial construction for carpenters - this is however made up for at the next stage of construction.

2. Has to be done right - a finishing team must know what they are doing, if they mess up, concrete re-work will slow progress down. (use experienced concrete finishers - which you would do anyway).

From the contractors Perspective

For not having a kicker - Pros:

1. Faster (INITIAL)construction, but risky. (however, many contractors cast a kicker at the second stage but this increases the number of joints in the concrete WHICH IS NOT GOOD). You will lose this time easily with all the re-work.

For not having a Kicker - Cons:

1. Any mistakes in the steel reinforcement could prove costly, whole gridlines in the wrong location may involve structural engineering to fix.

2. Cover issues may need re-work.

3. Increases the number of joints in the concrete.

4. Once the concrete is poured and has set, mistakes require costly rework and potential structural engineering.

It is always best to have a kicker, you can see any alignment or cover issues straight away and fix them. Any time lost through making kickers is always made up at the next stage. You simply butt up to your formwork against the kicker and plumb down for verticality. (don't forget your top column alignment.)

Not having a kicker is risky, best to take your time and get it right. Don't use inexperienced crews for concrete finishing, this is an added risk (and re-work) factor you don't need.


No comments:

Post a Comment